Secant Piled Walls

A secant piled wall is formed by constructing alternative interlocking primary and secondary bored piles as a retaining structure providing load bearing walls and deep foundations for engineering construction.

What is a secant piled wall?

A secant pile wall is a bored pile retaining wall formed by the installation of interlocking primary and secondary piles. This creates a continuous retaining structure, to support excavation and to mitigate the ingress of water.

Secant walls are relatively flexible in shape and design, offering benefits over diaphragm walls. They are also able to provide higher capacities (including lateral) than are typically possible with sheet pile walls.

There are three types of Primary piles as identified below:

Soft: Typically, a bentonite / grout mix.

Firm: Usually a C8/10 or P280 concrete

Hard: Structural Concrete

For Soft/Firm piles they are considered non-structural and are there to provide the water proofing only. Hard Primary piles are structural elements that often contain concrete and a reinforcing cage, as well as providing the water proofing element.

Secondary piles are the main structural element and are always classed as “Hard”. These are formed using structural concrete and a steel reinforcement cage.

These walls can be formed by a number of bored methodologies, including CFA, SFA, Bored Cast-in-Place and Cased CFA (to limited depths). Cased CFA is generally only used for secant walls, providing better verticality tolerance than CFA, whilst maintaining higher productions than Bored Cast-in-Place.

Key capabilities:

  • Rig loadings: 6–140 tonnes
  • Diameter:
    • 300–1,200mm to depth of 40m, diameter dependent, using CFA techniques
    • 300 – 2,100mm to a depth of 65m using rotary bored piling techniques

What are the advantages of Secant Piled Walls?

  • Flexibility to maximise land use, fits complex site boundaries and weave between underground structures
  • Can be installed as a cantilever section as a propped wall, using permanent anchors or temporary propping
  • Higher vertical tolerances can be achieved when using segmental casing during the installation of the secondary piles
  • Provides a water tight retaining structure, subject to the specified Grade

Common Uses

  • Temporary or permanent water-tight retaining walls
  • Slope stabilisation
  • Water cut off for drainage channels
  • Enable and support excavations
  • Basements and underground car parks

Prior to commencing with pile installation, a scalloped guide wall is installed to ground level providing line and level. Piles can be constructed using CFA, cased CFA or rotary bored techniques or a combination of methods.

Pile installation commences with the installation of a series of primary (female) piles installed through the guide wall. After the primary piles have gained sufficient strength, the interlocking secondary (male) piles are then installed cutting partially into the primary piles on either side. The primary piles contain full length reinforcement and are cast with high strength concrete. This installation process is continued until a continuous homogeneous structure is formed.

Van Elle Secant Piled Walls